Please see below of recent newsletters released on the progress of the Belmont Demolition and Clean-up.
Key dates June - September, 2017 – First Phase Remediation project Late 2017 – Main Remediation Project to be undertaken Remediation program The first phase of the remediation project at the former CSIRO research facility at 1 Henry Street Belmont is progressing well and expected to be completed next month[...]
Key dates June - September, 2017 – First Phase Remediation project Late 2017 – Main Remediation Project to be undertaken Demolition update The clean-up of the former CSIRO research facility at 1 Henry Street Belmont is on track and expected to be completed in the first quarter of 2018[...]
Community update Demolition work at the CSIRO Belmont site is progressing well and is on track for the planned March 2017 completion. The former CSIRO Textile and Fibre Technology Laboratory has been sold to development company Up Property, who intend to develop the site for residential use. Demolition of the 6.2 hectare property started in July[...]